Skyline rail, Honolulu
An 18.9 mile, 19-station elevated rail line. Segments 1 and 2 are open; Segment 3 is under construction.
Show on the map: Skyline rail, Honolulu (HART Recovery Plan scope)
- Investment$9.93 billion, the 2022 Recovery Plan total including $785 million of financing costs, the figure used on the mapHonolulu Authority for Rapid Transportation, 2022
- Scope18.9 miles and 19 stations from East Kapolei to Civic Center, the Recovery Plan scope later included in the 2024 amended Full Funding Grant AgreementHonolulu Authority for Rapid Transportation, Nov 23, 2026
- Open segmentsPassenger service is open from East Kapolei to the Kalihi Transit Center, covering Segments 1 and 2Honolulu Authority for Rapid Transportation, Nov 23, 2026
- Segment 3About three miles of elevated guideway and six stations, from Kalihi to Civic Center, now under construction. Guideway and station construction is scheduled for completion in 2030, with passenger service anticipated in 2031Honolulu Authority for Rapid Transportation, Nov 23, 2026
Next gate
Dillingham utility work finished
Expected in late 2026
HART says utility relocation and roadway restoration along Dillingham Boulevard are expected to be completed in late 2026. Schedules are subject to change.
Every step so far, and what comes next
-
DoneSeptember 2022
Recovery Plan accepted
The FTA accepted HART's 2022 Recovery Plan, which shortened the funded line to Civic Center.
Source: Honolulu Authority for Rapid Transportation, Nov 23, 2026
-
DoneJune 2023
Segment 1 opened
Skyline began passenger service from East Kapolei to Aloha Stadium.
Source: Honolulu Authority for Rapid Transportation, Nov 23, 2026
-
DoneFebruary 2024
Amended federal grant signed
The mayor and HART's CEO signed an amended Full Funding Grant Agreement with the FTA.
Source: Honolulu Authority for Rapid Transportation, Nov 23, 2026
-
DoneOctober 2025
Segment 2 opened
Service extended from Aloha Stadium to the Kalihi Transit Center, including the airport. Column shaft work began on the City Center segment.
Source: Honolulu Authority for Rapid Transportation, Nov 23, 2026
-
DoneApril 2026
Chinatown station foundations
HART said station foundation work began in the Chinatown area.
Source: Honolulu Authority for Rapid Transportation, Nov 23, 2026
-
NextLate 2026
Dillingham utility work finished
Utility relocation and roadway restoration along Dillingham Boulevard are expected to be completed in late 2026.
Source: Honolulu Authority for Rapid Transportation, Nov 23, 2026
-
Expected2030
Segment 3 construction complete
HART's published target for finishing Segment 3 guideway and station construction.
Source: Honolulu Authority for Rapid Transportation, Nov 23, 2026
-
Expected2031
Segment 3 passenger service
Passenger service is anticipated in 2031. HART also cites a March 2031 operational readiness date for the Recovery Plan scope.
Source: Honolulu Authority for Rapid Transportation, Nov 23, 2026
Worth knowing
- The map uses the Recovery Plan figure of $9.93 billion, including $785 million of financing costs. This is not the cost of the unfunded extension to Ala Moana.
- In August 2026, Honolulu Civil Beat reported that HART's CEO said the official budget was $10.079 billion and that a risk estimate could go higher. This page keeps the Recovery Plan figure used on the map.
- Kakaako, Ala Moana and the Pearl Highlands parking garage were postponed and are not in the current funded scope.
- The pin is near Kalihi. The line spans many stations.
- Dates are agency targets.
Last checked Nov 23, 2026. We add a step when it happens and link the source.