Smarr Combined-Cycle plant
A $3.3 billion, 1,425 megawatt combined-cycle natural gas plant that officially broke ground on May 7, 2026, with commercial operation expected in 2029.
Show on the map: Smarr Combined-Cycle plant
- InvestmentOglethorpe Power's May 7, 2026 groundbreaking release described a $3.3 billion investment in Monroe County, the figure used on the map. The company's project page uses the rounded wording of a capital investment of more than $3 billion, which is consistent with that $3.3 billion figure and is not treated as a second official costOglethorpe Power, May 7, 2026
- ScopeThe official project page describes a two-unit combined-cycle natural gas plant with 1,425 megawatts of capacity, using GE Vernova 7HA.03 gas turbines, with Kiewit subsidiary The Industrial Company as the engineering, procurement, and construction partner. The plant will be built on land already owned by Oglethorpe Power, near the existing Smarr Energy FacilityOglethorpe Power, Nov 23, 2026
- Groundbreaking and scheduleOglethorpe Power broke ground on May 7, 2026. The official project page says onsite work began in September 2025, with commercial operation expected in 2029. The groundbreaking release said the project will employ as many as 1,200 workers during peak construction and about 30 full-time employees once operationalOglethorpe Power, May 7, 2026
Next gate
Commercial operation targeted
2029
Official Oglethorpe Power materials say commercial operation is expected in 2029.
Every step so far, and what comes next
-
DoneSeptember 2025
Onsite work began
Oglethorpe Power's official project page says onsite work began in September 2025.
Source: Oglethorpe Power, Nov 23, 2026
-
DoneMay 7, 2026
Official groundbreaking
Oglethorpe Power broke ground on the $3.3 billion Smarr Combined-Cycle facility in Monroe County.
Source: Oglethorpe Power, May 7, 2026
-
Next2029
Commercial operation targeted
Official materials say the plant is projected to come online in 2029.
Source: Oglethorpe Power, May 7, 2026
Worth knowing
- The map figure is the official $3.3 billion investment in the May 7, 2026 groundbreaking release. Later financing, including any Rural Utilities Service loan, is not added to the pin.
- The project page wording of more than $3 billion is a rounded floor, not a separate official total.
- Other Oglethorpe Power generation projects, including any separate unit at Talbot, are not included in this pin.