New Lock at the Soo
A second Poe-sized lock, 1,200 feet long, under construction in the footprint of the 1919 Sabin Lock, with official Corps materials saying the project remains on track for completion in 2030.
Show on the map: New Lock at the Soo
- Investment, as used on the mapThe map uses $2.62 billion, recorded in the underlying data as $2.619 billion, for the New Lock at the Soo. Official Corps pages reviewed this pass did not restate that exact figure. A December 27, 2022 official Detroit District release said the project was reauthorized in the Water Resources Development Act of 2022 at $3.219 billion. This page keeps the map figure and records that official authorization amount in the caveatsU.S. Army Corps of Engineers, Detroit District, Dec 27, 2022
- ScopeOfficial Corps project materials say the new lock will be the same dimensions as the Poe Lock, 1,200 feet long, 110 feet wide, and 32 feet deep, and is being built in the footprint of the existing Sabin Lock, which opened in 1919, to provide a second Poe-sized lock at Sault Ste. MarieU.S. Army Corps of Engineers, Great Lakes and Ohio River Division, Mar 4, 2026
- Construction status and scheduleThe official project page, updated March 4, 2026, says major construction continues on Phase 3 and remains on schedule for a 2030 completion. A June 16, 2025 official release said Phase 1 upstream channel deepening was completed in 2022, Phase 2 upstream approach walls were completed in 2024, the Phase 3 base contract was awarded in July 2022 at $1.068 billion, and remaining Phase 3 options totaling $95.3 million were awarded that June to Kokosing Alberici Traylor, with the project on track for completion in 2030. A Corps stakeholder update lists an estimated completion of summer 2030U.S. Army Corps of Engineers, Detroit District, Jun 16, 2025
Next gate
Completion targeted
2030, with a stakeholder update listing summer 2030
Official Corps project and news pages say the project remains on track for completion in 2030. A Corps stakeholder update lists the estimated completion as summer 2030.
Every step so far, and what comes next
-
DoneJuly 2022
Phase 3 base contract awarded
The Corps said the Phase 3 base contract was awarded at $1.068 billion in July 2022, and that Phase 3 construction began in late 2022.
Source: U.S. Army Corps of Engineers, Detroit District, Jun 16, 2025
-
DoneJune 16, 2025
Remaining Phase 3 options awarded
The Detroit District awarded $95.3 million in remaining Phase 3 options and said the project continued to be on track for completion in 2030.
Source: U.S. Army Corps of Engineers, Detroit District, Jun 16, 2025
-
DoneAs of the official project page updated March 4, 2026
Phase 3 major construction continuing
The official Corps project page said major construction was continuing on Phase 3 and remained on schedule for a 2030 completion.
Source: U.S. Army Corps of Engineers, Great Lakes and Ohio River Division, Mar 4, 2026
-
Next2030
Completion targeted
Official Corps materials say the project is on track for completion in 2030, and a stakeholder update lists summer 2030.
Source: U.S. Army Corps of Engineers, Great Lakes and Ohio River Division, Mar 4, 2026
Worth knowing
- The map figure is $2.62 billion. This pass did not find that exact certified total restated on a first-party Corps page. Official Corps materials reviewed here include the December 2022 WRDA 2022 authorization of $3.219 billion and later contract-award amounts. The map figure is left unchanged and is not replaced with the 2022 authorization amount or with a sum of individual contract awards.
- A September 2025 trade-press report citing a revised Corps estimate was not used as a source.
- The $1.068 billion Phase 3 base contract and $95.3 million in later options are contract awards within the project, not a substitute for the map total.
Last checked Nov 23, 2026. We add a step when it happens and link the source.