South System Expansion 4 Project
A July 31, 2026 FERC order issued certificates for Southern Natural Gas's South System Expansion 4 Project, with Southern estimating the total cost of its portion at $3,298,000,000.
Show on the map: South System Expansion 4 Project
- Official costThe official July 31, 2026 FERC order issuing certificates in Docket Nos. CP25-514-000 and CP25-517-000, 196 FERC 61,093, states that Southern estimates the total cost of its portion of the SSE4 Project to be $3,298,000,000, the figure used on the map. The same official paragraph says Southern proposes to allocate $88,100,000 of compression costs at the Wrens, Hall Gate, Gallion, and Enterprise compressor stations to its current customers as replacement costs, with the remaining $3,209,900,000 allocated to SSE4 project shippers. That official $88,100,000 amount is included in the $3,298,000,000 total and is not a second project.Federal Energy Regulatory Commission, Jul 31, 2026
- ScopeThe official order says the SSE4 Project would provide approximately 1.323 million dekatherms per day of incremental firm transportation service on Southern's existing system and 460,300 dekatherms per day on Elba Express's existing system, from a new interconnection with Tennessee Gas's proposed Mississippi Crossing Project and existing receipt points on Southern's system, to delivery points in the Southeast. For Southern's portion, the order describes 22 natural gas pipeline loops totaling approximately 291 miles, consisting of 14 segments ranging from 20 to 42 inches in diameter, along Southern's existing South Main Line in Mississippi, Alabama, and Georgia, plus added compression at existing stations including Rose Hill, Enterprise, York, and other official stations named in the order.Federal Energy Regulatory Commission, Jul 31, 2026
- Elba Express and Mississippi Crossing not addedThe same official order states that Elba Express estimates the total cost of its portion of the SSE4 Project to be $160,000,000. That official amount is under $1 billion and is not added into this pin. The Mississippi Crossing Project, certificated in the same order for Tennessee Gas, is a separate map pin and is not re-added here.Federal Energy Regulatory Commission, Jul 31, 2026
- Certificate conditionThe official order issues a certificate of public convenience and necessity to Southern authorizing it to construct and operate its portion of the SSE4 Project, conditioned on completion of construction and making the facilities available for service within three years of the date of the order. This pass did not find an official construction start in that order. The map pin remains listed as permitted.Federal Energy Regulatory Commission, Jul 31, 2026
Next gate
Official certificate requires the facilities to be available for service within three years of the order
After the official July 31, 2026 FERC certificate
The official order conditions Southern's certificate on completing construction and making the facilities available for service within three years of July 31, 2026. This pass did not find an official construction start in that order. The map pin remains listed as permitted.
Every step so far, and what comes next
-
DoneJuly 31, 2026
FERC issues certificates for the South System Expansion 4 Project
The official FERC order issued a certificate to Southern Natural Gas to construct and operate its portion of the SSE4 Project, stating that Southern estimates the total cost of its portion at $3,298,000,000, the figure used on the map, and conditioned the certificate on making the facilities available for service within three years of the order.
-
NextAfter the official July 31, 2026 FERC certificate
Official certificate requires the facilities to be available for service within three years of the order
The official order conditions Southern's certificate on completing construction and making the facilities available for service within three years of July 31, 2026. This pass did not find an official construction start in that order. The map pin remains listed as permitted.
Worth knowing
- The map figure is Southern's official estimated total cost of its portion of the SSE4 Project, $3,298,000,000, as stated in the July 31, 2026 FERC certificate. The official $88,100,000 allocated to current customers as replacement costs is included in that total and is not a second project.
- Elba Express's official estimated cost of its portion of the same project, $160,000,000, is not added into this pin. The related Mississippi Crossing Project, certificated in the same order, is a separate map pin and is not re-added.
- The official order requires the Southern facilities to be completed and available for service within three years of July 31, 2026. This pass did not find an official construction start in that order. The map pin remains listed as permitted, and this page does not change any map usd or stage field.