Southeast Supply Enhancement Project
A January 29, 2026 FERC order issued a certificate for Transco's Southeast Supply Enhancement Project, stating that the proposed facilities will cost $1,527,002,037.
Show on the map: Southeast Supply Enhancement Project
- Official costThe official January 29, 2026 FERC order issuing a certificate in Docket No. CP25-10-000, 194 FERC 61,078, states that Transco estimates the total cost of the project to be approximately $1.527 billion, and later states that the proposed facilities will cost $1,527,002,037, the exact official figure used on the map. The same official order says Transco proposes to allocate $75,812,961 of that amount as replacement costs at Compressor Station 145, which would be borne by existing customers. That official replacement amount is included in the $1,527,002,037 total and is not a second project.Federal Energy Regulatory Commission, Jan 29, 2026
- ScopeThe official order says the project is designed to provide up to 1,596,900 dekatherms per day of firm transportation capacity from Transco's existing Station 165 Zone 5 pooling point and the Cherrystone Interconnect with Mountain Valley Pipeline in Pittsylvania County, Virginia, to natural gas markets in the Southeast. Official facilities include the 31.2-mile Eden Loop in Pittsylvania County, Virginia, and Rockingham County, North Carolina, and the 24.1-mile Salem Loop in Guilford, Forsyth, and Davidson Counties, North Carolina, along with other official facilities described in the order, including new compression and piping modifications at existing stations.Federal Energy Regulatory Commission, Jan 29, 2026
- Certificate conditionThe official order issues a certificate of public convenience and necessity to Transco, conditioned on completing construction of the proposed facilities and making them available for service within two years of the date of the order. This pass did not find an official construction start in that order. The map pin remains listed as permitted.Federal Energy Regulatory Commission, Jan 29, 2026
Next gate
Official certificate requires the facilities to be available for service within two years of the order
After the official January 29, 2026 FERC certificate
The official order conditions Transco's certificate on completing construction and making the facilities available for service within two years of January 29, 2026. This pass did not find an official construction start in that order. The map pin remains listed as permitted.
Every step so far, and what comes next
-
DoneJanuary 29, 2026
FERC issues a certificate for the Southeast Supply Enhancement Project
The official FERC order issued a certificate to Transco to construct and operate the Southeast Supply Enhancement Project, stating that the proposed facilities will cost $1,527,002,037, the figure used on the map, and conditioned the certificate on making the facilities available for service within two years of the order.
-
NextAfter the official January 29, 2026 FERC certificate
Official certificate requires the facilities to be available for service within two years of the order
The official order conditions Transco's certificate on completing construction and making the facilities available for service within two years of January 29, 2026. This pass did not find an official construction start in that order. The map pin remains listed as permitted.
Worth knowing
- The map figure is the exact official project cost of $1,527,002,037 stated in the January 29, 2026 FERC certificate, which the order also describes as approximately $1.527 billion. The official $75,812,961 allocated as replacement costs at Compressor Station 145 is included in that total and is not a second project. This page does not change any map usd field.
- The official order requires the facilities to be completed and available for service within two years of January 29, 2026. This pass did not find an official construction start in that order. The map pin remains listed as permitted, and this page does not change any map stage field.