Track your favorite projects · Infrastructure
SR 400 Express Lanes, metro Atlanta
16 miles of tolled express lanes on Georgia 400, now under construction and aimed at opening in 2031.
Show on the map: SR 400 Express Lanes, metro Atlanta
- CostAbout $11 billion, Georgia DOT's estimate for the public-private projectGeorgia Department of Transportation, Mar 23, 2026
- Length16 miles of tolled express lanes, two in each direction to McGinnis Ferry Road and one in each direction from there to McFarland ParkwayGeorgia Department of Transportation, Mar 23, 2026
- OpeningLanes are expected to open to traffic in 2031Georgia Department of Transportation, Mar 23, 2026
- ConcessionThe developer is to operate and maintain the lanes for 50 years after they open, then hand the corridor back to the stateGeorgia Department of Transportation, Mar 23, 2026
Next gate
Lanes open to traffic
2031
Georgia DOT's published target for service to begin. The FAQ notes that the schedule can change.
Every step so far, and what comes next
-
DoneAugust 2025
Financial close
The project reached financial close, and the developer made a $3.8 billion concession payment to Georgia DOT.
-
DoneApril 22, 2026
Construction begins
SR 400 Peach Partners and Georgia DOT held a groundbreaking in Alpharetta and said construction was officially under way.
Source: ACCIONA, Apr 22, 2026
-
Next2031
Lanes open to traffic
Georgia DOT's target for service commencement.
Worth knowing
- ACCIONA described the investment as about $10.8 billion at the April 2026 groundbreaking. The map uses Georgia DOT's $11 billion estimate.
- The schedule is subject to change.
Last checked Nov 23, 2026. We add a step when it happens and link the source.