Stargate Abilene

Crusoe, with Blue Owl and Primary Digital; used by Oracle and OpenAI · Lancium Clean Campus, Abilene, Taylor County, Texas

Mostly delivered, last buildings finishing

The first Stargate campus, eight buildings and 1.2 GW built by Crusoe for Oracle and OpenAI.

Show on the map: Abilene AI data center (Stargate site)

Next gate

Full campus done

First quarter of 2027

Crusoe said in March 2026 that construction of the eight buildings would run through the first quarter of 2027.

Every step so far, and what comes next

  1. DoneJun 2024

    Phase 1 construction starts

    Two buildings and 200+ MW.

  2. DoneMar 2025

    Phase 2 construction starts

    Six more buildings, taking the campus to 1.2 GW.

  3. DoneMay 21, 2025

    $15 billion joint venture

    Crusoe, Blue Owl and Primary Digital funded the second phase.

  4. DoneSep 30, 2025

    First two buildings live

    Phase 1 began running Oracle Cloud workloads.

  5. DoneSep 10, 2026

    Six of eight delivered

    Oracle said six buildings had been delivered.

  6. NextQ1 2027

    Construction wraps

    Crusoe's stated timeline for all eight buildings.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.