Track your favorite projects · AI data centers
Stargate Michigan, "The Barn"
Three single-story data center buildings with more than 1 GW, built for Oracle's work with OpenAI.
Show on the map: Stargate data center, Saline Township
- Investment$43.1 billion, the total estimated project cost in Oracle's Industrial Facilities Exemption application ($9.9202 billion in real property improvements and $33.1777 billion in personal property)Saline Township Board of Trustees, Nov 11, 2026
- Financing$16 billion announced in April 2026, financed by Related Digital, Blackstone funds and PIMCO-led debtRelated Companies, Apr 24, 2026
- CapacityMore than 1 GW across three buildingsRelated Companies, Apr 24, 2026
- Jobs2,500+ union construction jobs and 450+ jobs on siteRelated Companies, Apr 24, 2026
- PowerDTE supplies 100% of the power, with new battery storage paid for by OracleRelated Companies, Apr 24, 2026
Next gate
State tax decision
Not yet scheduled
The 12-year, 50% tax break the township reaffirmed on Nov 11 still needs State Tax Commission approval.
Every step so far, and what comes next
-
DoneOct 15, 2025
Industrial district created
The township set up the district after settling a lawsuit by the developer.
Source: MLive, Nov 12, 2026
-
DoneFeb 6, 2026
Construction began
The IFEC application, as recited in the township's Nov 11, 2026 resolution, states that construction and installation began on Feb 6, 2026.
-
DoneApr 24, 2026
Financing announced
Related Digital and Blackstone announced financing; construction on the first buildings was underway.
Source: Related Companies, Apr 24, 2026
-
DoneNov 11, 2026
Tax break reaffirmed
The township board ratified and confirmed approval of Oracle's IFEC application, which lists a total estimated project cost of $43,097,900,000, and a 12-year, 50% tax abatement after completion. State Tax Commission approval is still required.
-
NextPending
State Tax Commission
The abatement needs state approval.
Source: MLive, Nov 12, 2026
Worth knowing
- The map uses $43.1 billion, the total estimated project cost in Oracle's IFEC application, ratified by the Saline Township Board on Nov 11, 2026. MLive has also reported the project at about $43 billion.
- Related Digital's April 2026 announcement was $16 billion in financing, a different figure from the IFEC investment total.
- The IFEC application does not include electrical substation improvements on Units 13 and 14 of the Saline Data Center Condominium.
- Opponents dispute the township's procedures on the tax break.
Last checked Nov 23, 2026. We add a step when it happens and link the source.