StarPlus Energy gigafactories, Kokomo
Two joint-venture lithium-ion battery plants in Kokomo, with a combined official investment of more than $6.3 billion.
Show on the map: StarPlus Energy gigafactories, Kokomo
- InvestmentOver $6.3 billion for both Kokomo plants, the figure used on the map. The second plant alone was described as an investment of over $3.2 billionStellantis, Oct 11, 2023
- Capacity and jobsCombined annual capacity of 67 gigawatt hours (33 GWh at the first plant and 34 GWh at the second) and 2,800 jobs (1,400 at each plant)Stellantis, Oct 11, 2023
- Plant 1, company siteStarPlus Energy's Solutions page lists a Plant 1 production start date of 2024 and 1,400 jobsStarPlus Energy, Nov 23, 2026
- Plant 1, 2023 planThe October 2023 Stellantis release said the first plant was on track to start production in the first quarter of 2025, with annual capacity of 33 gigawatt hoursStellantis, Oct 11, 2023
- Plant 2The October 2023 Stellantis release said the second plant was planned to start production in early 2027, with annual capacity of 34 gigawatt hours and 1,400 jobsStellantis, Oct 11, 2023
Next gate
Plant 2 production start
Early 2027
Stellantis's October 11, 2023 release said the second Kokomo gigafactory was expected to begin production in early 2027. StarPlus Energy's Battery Production page still lists 2027 as the Plant 2 start date.
Every step so far, and what comes next
-
DoneOctober 11, 2023
Second Kokomo plant announced
Stellantis and Samsung SDI chose Kokomo for a second StarPlus Energy gigafactory, bringing the combined investment to over $6.3 billion.
Source: Stellantis, Oct 11, 2023
-
Done2024 to 2025
Plant 1 production start listed as 2024
StarPlus Energy's Solutions page lists a Plant 1 production start date of 2024.
Source: StarPlus Energy, Nov 23, 2026
-
NextEarly 2027
Plant 2 production start
The date given in the October 2023 announcement and still listed on StarPlus Energy's Battery Production page.
Source: Stellantis, Oct 11, 2023
Worth knowing
- The map counts $6.3 billion. The official wording is over $6.3 billion for both plants, from the 2023 announcement. This page has not found a later official combined cost update.
- Official company pages disagree on the Plant 1 start year. Stellantis in 2023 said first-quarter 2025. StarPlus About and Solutions pages now say 2024. The Battery Production page still says 2025. This page records the conflict rather than choosing a start date that is not clearly documented.
- The map stage is operating, which refers to the first plant. Plant 2 is still ahead of its published 2027 start.
Last checked Nov 23, 2026. We add a step when it happens and link the source.