Southwest Intertie Project-North (SWIP-North)
An official September 3, 2026 LS Power release, datelined Ely, Nevada, marked the start of construction on SWIP-North, a 285-mile, 500-kilovolt line and a $1 billion-plus investment, with completion expected in 2028.
Show on the map: Southwest Intertie Project-North (SWIP-North)
- Official cost, route, and construction startThe official September 3, 2026 LS Power news release, issued for its affiliate Great Basin Transmission and datelined Ely, Nevada, says a groundbreaking ceremony that day officially marked the start of construction on the Southwest Intertie Project-North, a new 285-mile, 500-kilovolt transmission line connecting the Midpoint Substation near Twin Falls, Idaho, with the Robinson Summit Substation near Ely, Nevada. The official release says the project represents a $1 billion-plus investment in power infrastructure. The map counts $1 billion and labels the pin $1B+. The official release also says construction on SWIP-North began in summer 2026 and is expected to be completed in 2028, and that more than 70 percent of SWIP-North will be built in Nevada.LS Power, Sep 3, 2026
Next gate
Official September 3, 2026 release said construction had started, with completion expected in 2028
After the official summer 2026 construction start and September 3, 2026 groundbreaking, toward the official 2028 completion
The official LS Power release marked the start of construction on the $1 billion-plus, 285-mile SWIP-North line and said construction began in summer 2026, with completion expected in 2028. The map pin remains listed as under construction.
Every step so far, and what comes next
-
DoneSummer 2026, with a groundbreaking ceremony on September 3, 2026
Construction starts on SWIP-North
The official LS Power release, datelined Ely, said a groundbreaking ceremony on September 3, 2026, officially marked the start of construction, and that construction began in summer 2026 on the 285-mile, 500-kilovolt line, a $1 billion-plus investment expected to be completed in 2028.
Source: LS Power, Sep 3, 2026
-
NextAfter the official summer 2026 construction start and September 3, 2026 groundbreaking, toward the official 2028 completion
Official September 3, 2026 release said construction had started, with completion expected in 2028
The official LS Power release marked the start of construction on the $1 billion-plus, 285-mile SWIP-North line and said construction began in summer 2026, with completion expected in 2028. The map pin remains listed as under construction.
Source: LS Power, Sep 3, 2026
Worth knowing
- The official release describes a $1 billion-plus investment. The map counts $1 billion and labels the pin $1B+. Official earlier phases of the broader Southwest Intertie corridor, including the One Nevada Transmission Line and DesertLink, are separate projects and are not added to this pin. This page does not change any map usd, stage, or pledge field.
Last checked Nov 24, 2026. We add a step when it happens and link the source.