T5 Data Centers Grayslake campus
T5's AI-ready data center campus on the Cornerstone property in Grayslake, first building under way.
Show on the map: T5 Data Centers Grayslake data center campus
- InvestmentAbout $18 billion, the village's estimate of private investmentLake and McHenry County Scanner, Sep 1, 2026
- Campus11 buildings and about 6.75 million square feet on about 473 acres in the current planPatch, Sep 1, 2026
- PowerAbout 1.55 GW supplied by ComEd in the approved planLake and McHenry County Scanner, Sep 1, 2026
- Local payoffThe village and developer estimate $1.4 billion in property taxes over 20 years and more than 1,000 permanent jobsFOX 32 Chicago, Nov 6, 2026
Next gate
Court ruling on the lawsuit
By Dec 30, 2026
A Lake County judge heard the village's motion to dismiss on Nov 6 and said she will rule in writing by Dec 30.
Every step so far, and what comes next
-
DoneSep 2024 to May 2025
Village approvals
The Grayslake Village Board approved the T5 @ Chicago IV campus in a series of votes.
-
DoneJul 2026
Lawsuit filed
Neighborhood groups sued the village and T5 to block the project.
Source: FOX 32 Chicago, Nov 6, 2026
-
DoneSep 1, 2026
First building permit
Grayslake issued the permit for the first 800,000 square foot building and site work began.
-
DoneOct 2026
Foundations going in
Foundation work on the first building was underway and a permit was issued for the campus electrical facility.
Source: Daily Herald, Oct 3, 2026
-
DoneNov 6, 2026
Motion to dismiss heard
The judge took the village's motion to dismiss under advisement.
Source: FOX 32 Chicago, Nov 6, 2026
-
NextBy Dec 30, 2026
Ruling on the lawsuit
The judge's written ruling is due.
Source: FOX 32 Chicago, Nov 6, 2026
Worth knowing
- The $18 billion is the village's estimate, not a committed figure from T5.
- Neighbors' lawsuit seeks to void the approvals; the ruling is due by Dec 30, 2026.
- The full campus is expected to take seven to 10 years, depending on leasing.
Last checked Nov 23, 2026. We add a step when it happens and link the source.