Track your favorite projects · Energy
TerraPower Natrium plant, Kemmerer
A 345 megawatt sodium-cooled reactor with molten-salt storage, now in nuclear construction after an NRC permit in March 2026, with completion planned in 2030.
Show on the map: TerraPower Natrium plant, Kemmerer
- InvestmentTerraPower's official FAQ says the first plant is being built through the Department of Energy's Advanced Reactor Demonstration Program, which authorizes a 50/50 cost share and up to $2 billion for the Natrium project, to be matched dollar for dollar by TerraPower and partners. The map counts $4 billion. TerraPower does not publish a single all-in project total on that pageTerraPower, Nov 23, 2026
- DesignThe plant is a 345 megawatt sodium-cooled fast reactor with an integrated molten-salt energy storage system that can boost output to 500 megawatts when needed, enough to power around 400,000 homes, according to TerraPower's April 23, 2026 construction announcementTerraPower, Apr 23, 2026
- NRC permitTerraPower's FAQ says the NRC voted on March 4, 2026, to award Kemmerer Unit 1 a construction permit under 10 CFR Part 50, the first commercial-scale advanced nuclear plant to receive that permit. A March 9, 2026 Department of Energy article confirmed the permit and said the project is expected to be completed in 2030TerraPower, Nov 23, 2026
- Construction startTerraPower announced the official start of construction on Kemmerer Unit 1 on April 23, 2026, after the NRC permit. The company said it had already broken ground on the greenfield site in June 2024 and begun construction on non-nuclear support facilities. About 1,600 workers were being mobilized for plant construction, with about 250 full-time staff expected once operationalTerraPower, Apr 23, 2026
Next gate
Operating license application, then completion
Operating license application anticipated in 2028; completion expected in 2030
TerraPower's FAQ says the company anticipates submitting the operating license application in 2028. The Department of Energy's March 9, 2026 article said the project is expected to be completed in 2030.
Every step so far, and what comes next
-
DoneJune 2024
Non-nuclear site work began
TerraPower broke ground on the greenfield site and began construction on non-nuclear support facilities, including a sodium test and fill facility and a training center.
Source: TerraPower, Nov 23, 2026
-
DoneMarch 4, 2026
NRC issues a construction permit
The NRC voted to award Kemmerer Unit 1 a construction permit, the first for a commercial-scale advanced nuclear plant under that framework.
Source: TerraPower, Nov 23, 2026
-
DoneApril 23, 2026
Nuclear plant construction begins
TerraPower announced the official start of construction on Kemmerer Unit 1.
Source: TerraPower, Apr 23, 2026
-
Next2028
Operating license application anticipated
The year given in TerraPower's official FAQ, ahead of an expected 2030 completion in the Department of Energy's March 2026 article.
Source: TerraPower, Nov 23, 2026
-
Expected2030
Project expected to be completed
The completion year given in the Department of Energy's March 9, 2026 article.
Source: U.S. Department of Energy, Office of Nuclear Energy, Mar 9, 2026
Worth knowing
- The map counts $4 billion. That is an implied total if the authorized $2 billion Department of Energy share is fully matched, not a published official all-in budget from TerraPower. Official materials describe a 50/50 cost share and up to $2 billion from DOE.
- Non-nuclear site work began in June 2024. This page treats nuclear plant construction as starting on April 23, 2026, after the NRC construction permit.
- The 2030 completion and 2028 operating-license filing are official targets and may move. The plant also still needs an NRC operating license before it can run.
Last checked Nov 23, 2026. We add a step when it happens and link the source.