The New SLC airport redevelopment
A 12-year, $5.1 billion rebuild of Salt Lake City's airport into 94 gates and 101 concessions, finished in October 2026.
Show on the map: The New SLC airport redevelopment
- Investment$5.1 billion, the figure used on the map and in the airport's October 28, 2026 completion releaseSalt Lake City International Airport, Oct 28, 2026
- ScopeA complete rebuild that replaced three aging terminals with a central terminal and two linear concourses, ending at 94 aircraft gates and 101 concessionsSalt Lake City International Airport, Oct 28, 2026
- ConstructionThe program broke ground in July 2014. Nearly 25,000 craft workers put in more than 18 million craft hoursSalt Lake City International Airport, Oct 28, 2026
- PhasingPhase 1 opened to passengers in September 2020, Phase 2 in October 2023, and Phase 3 in October 2024. Four additional gates opened in July 2026, and the remaining seven gates and six concessions opened on October 27, 2026Salt Lake City International Airport, Oct 28, 2026
- CompletionThe airport marked completion with a ribbon cutting around October 24, 2026, and said the remaining seven gates and six concessions opened on October 27, 2026Salt Lake City International Airport, Oct 28, 2026
Next gate
Commercial operation continues
In service, with the final gates open since October 27, 2026
The airport's October 28, 2026 release said the 12-year redevelopment program is complete, with 94 gates and 101 concessions in operation. No further construction on this program is described there.
Every step so far, and what comes next
-
DoneJuly 2014
Program groundbreaking
The New SLC Airport Redevelopment Program broke ground in July 2014.
-
DoneSeptember 2020 to October 2024
Phased openings
Phase 1 opened in September 2020, Phase 2 in October 2023, and Phase 3 in October 2024.
-
DoneOctober 27, 2026
Final gates and concessions opened
The remaining seven gates and six concessions opened, bringing the airport to 94 gates and 101 concessions.
-
NextIn service since October 27, 2026
Commercial operation continues
The airport marked the end of the 12-year program in its October 28, 2026 release.
Worth knowing
- The $5.1 billion figure is the official program cost in the airport's completion release.
- The map pin covers the completed redevelopment program, not later, separate airport projects that may follow.
Last checked Nov 23, 2026. We add a step when it happens and link the source.