Track your favorite projects · Semiconductors
Texas Instruments LFAB2
TI's second 300mm wafer fab in Lehi, still under construction and connected to the existing LFAB1 plant.
Show on the map: Texas Instruments LFAB2
- Investment$11 billion, which TI called the largest economic investment in Utah historyTexas Instruments, Nov 2, 2023
- JobsAbout 800 additional TI jobs, plus thousands of indirect jobs, per the 2023 groundbreakingTexas Instruments, Nov 2, 2023
- Federal awardUp to $1.6 billion in CHIPS funding for three new 300mm fabs, including cleanroom work and tool installation at LFAB2Texas Instruments, Dec 20, 2024
- SiteThe new fab connects to LFAB1. TI's Lehi page still described LFAB2 as under construction and showed October 2026 site photos.Texas Instruments, Oct 2026
Next gate
Cleanroom work and tool installation
No updated production date published
The CHIPS award supports cleanroom construction and tool installation at LFAB2. The 2023 groundbreaking said first production could come as early as 2026, but TI's Lehi page still called the fab under construction as of its October 2026 site photos.
Every step so far, and what comes next
-
DoneNov 2, 2023
Groundbreaking
TI broke ground on LFAB2 and said first production could come as early as 2026.
Source: Texas Instruments, Nov 2, 2023
-
DoneDec 20, 2024
CHIPS award agreement
Commerce awarded TI up to $1.6 billion for three new 300mm fabs, including cleanroom work and tool installation at LFAB2.
Source: Texas Instruments, Dec 20, 2024
-
DoneOctober 2026
Still under construction
TI's Lehi page described LFAB2 as under construction and posted October 2026 site photos.
Source: Texas Instruments, Oct 2026
-
NextNo updated date published
Cleanroom work and tool installation
The next work described in the CHIPS award. TI has not published a revised production date.
Source: Texas Instruments, Dec 20, 2024
Worth knowing
- The $11 billion figure is from the 2023 announcement.
- The $1.6 billion CHIPS award is for three fabs in Texas and Utah, not LFAB2 alone.
- TI has not published a revised first-production date on its 2026 Lehi page.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.