Transmission Initiative Down East (TIDE)
A $2.20 billion transmission proposal that ISO New England selected on August 14, 2026, as its preferred longer-term solution, with construction targeted to start in the first quarter of 2029 and service in the fourth quarter of 2032.
Show on the map: Transmission Initiative Down East (TIDE)
- Selection and costIn its August 14, 2026 official report on the 2025 Longer-Term Transmission Planning request for proposals, ISO New England selected Longer-Term Proposal A1, submitted by Central Maine Power as lead sponsor with Public Service New Hampshire and NSTAR Electric Company (collectively Eversource), as the preferred Longer-Term Transmission Solution. The official report lists the installed cost, as provided by the qualified transmission project sponsor, at $2.20 billion, the figure rounded to $2.2 billion on the mapISO New England, Aug 14, 2026
- ScopeThe official design summary for proposal A1 includes a wind interconnection point at Pittsfield, Maine; new 345 kilovolt lines from Pittsfield to Coopers Mills and from Buxton to Deerfield, New Hampshire, totaling 70 miles; a rebuild of the Larrabee Road to Surowiec 115 kilovolt line to operate at 345 kilovolts; and several reconductored 345 and 115 kilovolt lines. The request for proposals required new infrastructure at Pittsfield, or an alternate location north of the Albion Road substation, that can accommodate the interconnection of at least 1,200 megawatts of onshore windISO New England, Aug 14, 2026
- ScheduleThe official report lists a construction start in the first quarter of 2029 and an in-service date in the fourth quarter of 2032ISO New England, Aug 14, 2026
Next gate
Construction targeted to start
First quarter of 2029
ISO New England's official August 14, 2026 report lists a construction start in the first quarter of 2029 and an in-service date in the fourth quarter of 2032. This pass did not find a later official construction start.
Every step so far, and what comes next
-
DoneAugust 14, 2026
ISO New England selected proposal A1
The official evaluation report selected the Central Maine Power and Eversource $2.20 billion proposal as the preferred longer-term transmission solution.
Source: ISO New England, Aug 14, 2026
-
NextFirst quarter of 2029
Construction targeted to start
The official report lists construction starting in the first quarter of 2029, with an in-service date in the fourth quarter of 2032.
Source: ISO New England, Aug 14, 2026
Worth knowing
- The map figure is the $2.20 billion installed-cost estimate the sponsors provided to ISO New England, labeled $2.2 billion on the map. That is an estimate at the proposal stage, not a completed construction budget.
- The official ISO New England report identifies the selected project as Longer-Term Proposal A1. The map uses the name Transmission Initiative Down East (TIDE).
- The pin is approximate, at the planned wind interconnection point in Pittsfield. Official materials describe work in Maine and New Hampshire.
- The tracker stage notes ISO New England's selection. The map pin remains listed as announced, and this page does not change any map stage field.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.