Tolk Station Combustion Turbine Project
A permitted 928 megawatt simple-cycle dual-fuel combustion turbine plant at SPS's existing Tolk station, with an official recoverable capital-cost cap of $1,898,468,484 set by the Public Utility Commission of Texas on October 15, 2026.
Show on the map: Tolk Station Combustion Turbine Project
- Certificate and official cost capThe Public Utility Commission of Texas's October 15, 2026 official order in Docket 58664 amends Southwestern Public Service Company's certificate to authorize construction of the Tolk Station Combustion Turbine project. Finding of fact 181 sets the capital costs for which SPS may seek recovery and a return, inclusive of AFUDC, transmission upgrade and interconnection costs, and contingencies, at a cap of $1,898,468,484, the figure rounded to $1.90 billion on the map. Findings 176, 179, and 180 state that the company's estimated cost, inclusive of those same items, was $2,189,173,957, that the company estimate included an unreasonably high amount of contingency, and that the Commission capped contingency at 10% in setting the official recoverable cap. The official cap, not the higher company estimate, is the map figure.Public Utility Commission of Texas, Oct 15, 2026
- Scope and scheduleFinding of fact 28 states that the project would be located in Lamb County, Texas, at SPS's existing Tolk generating station, with a nameplate capacity of 928 megawatts, four combustion turbines with dual-fuel capability, and gas pipeline interconnection facilities. The same official finding describes a partial commercial operation date of April 2029 for certain turbines and a total estimated cost of approximately $1.91 billion excluding AFUDC. This pass did not find a later official confirmation that construction had begun after the October 15, 2026 order. The map pin remains listed as permitted. This plant is distinct from the existing coal-fired units at Tolk station, and it is one of several separately identified self-build facilities approved in the same docket; only this plant's official cap is included here.Public Utility Commission of Texas, Oct 15, 2026
Next gate
Partial commercial operation targeted for certain turbines
April 2029, according to official finding of fact 28
The official October 15, 2026 order describes a partial commercial operation date of April 2029 for certain turbines. This pass did not find a later official construction-start confirmation. The map pin remains listed as permitted.
Every step so far, and what comes next
-
DoneOctober 15, 2026
Commission authorizes the plant and sets a $1,898,468,484 official cost cap
The Public Utility Commission of Texas amended SPS's certificate to authorize the 928 megawatt Tolk Station CT project and capped recoverable capital costs at $1,898,468,484, the figure used on the map.
-
NextApril 2029, according to official finding of fact 28
Partial commercial operation targeted for certain turbines
The official order describes a partial commercial operation date of April 2029 for certain turbines. The map pin remains listed as permitted.
Worth knowing
- The map figure is the official recoverable capital-cost cap of $1,898,468,484 in finding of fact 181, labeled $1.90 billion, inclusive of AFUDC, transmission upgrade and interconnection costs, and contingencies. Official findings also state a company estimate of approximately $1.91 billion excluding AFUDC and $2,189,173,957 including AFUDC. Those official estimates are recorded here and are not used to replace the official cap used on the map.
- The same official docket also authorizes other separately identified generation projects, including the Gaines County CT project, which has its own official cap and its own tracker page. Those other projects are not added to this pin.
- This pass did not find a later official confirmation that construction had begun after the October 15, 2026 order. The map pin remains listed as permitted, and this page does not change any map stage field.