Track your favorite projects · Transmission
TransWest Express transmission line
Under construction
A 732-mile high-voltage line from south-central Wyoming through Colorado and Utah to southern Nevada.
Show on the map: TransWest Express
- Figure$3 billionCalifornia ISO, Jul 24, 2023
- What gets builtA 732-mile high-voltage line from south-central Wyoming through Colorado and Utah to southern NevadaCalifornia ISO, Jul 24, 2023
Next gate
First elements in service
2031 (planned)
TransWest plans to place the first elements of the line in service in 2031.
Every step so far, and what comes next
-
DoneJuly 24, 2023
Under construction
Construction began in 2023 with terminal and substation grading; the first elements are planned for service in 2031.
Source: California ISO, Jul 24, 2023
-
Next2031 (planned)
First elements in service
TransWest plans to place the first elements of the line in service in 2031.
Source: California ISO, Jul 24, 2023
Worth knowing
- CAISO calls it the $3 billion project; the developer's own site says multibillion-dollar.
- TransWest's February 2026 report to WECC says construction started in 2023 and the first elements are planned for service in 2031.
- Pin at the Wyoming terminal near Sinclair; the line runs through Colorado and Utah to southern Nevada.
Last checked Nov 28, 2026. We add a step when it happens and link the source.