UCSF Benioff Children's Hospital Oakland modernization
A permitted $1.62 billion modernization of the 11-acre Oakland campus, including a seven-story, 277,500 square-foot hospital building approved by the UC Regents on July 18, 2024, with opening planned for 2030.
Show on the map: UCSF Benioff Children's Hospital Oakland modernization
- Investment and approvalAn official July 18, 2024 UC San Francisco news release says the University of California Board of Regents that day approved a $1.49 billion hospital building on the Oakland campus of UCSF Benioff Children's Hospitals. The same official release says the hospital building is the keystone project in a $1.62 billion modernization effort on the 11-acre Oakland site, the figure used on the map. In addition to the new hospital building, the official release says the work includes a new administrative building, new MRI and other emergency-department equipment, renovations in the existing patient tower and diagnostic and treatment building, infrastructure upgrades, a new parking garage, and a relocated helistop.UC San Francisco, Jul 18, 2024
- Scope and scheduleThe official release describes a seven-story, 277,500 square-foot building with a new and expanded emergency department providing double the current space, a new neonatal intensive care unit, and seven new surgical suites. It says the new facility will open in 2030. The official release also says the UC Regents certified the environmental impact report and approved UCSF's long-range development plan for the area. This pass did not find a later official construction-start confirmation in that approval release. The map pin remains listed as permitted.UC San Francisco, Jul 18, 2024
Next gate
Opening planned
2030, according to the official July 18, 2024 UCSF release
The official Regents-approval release says the new facility will open in 2030. This pass did not find a later official construction-start confirmation in that release. The map pin remains listed as permitted.
Every step so far, and what comes next
-
DoneJuly 18, 2024
UC Regents approve the $1.62 billion Oakland campus modernization
The official UCSF release says the Board of Regents approved a $1.49 billion hospital building as the keystone of a $1.62 billion site modernization, the figure used on the map, with opening planned for 2030.
Source: UC San Francisco, Jul 18, 2024
-
Next2030, according to the official July 18, 2024 release
Opening planned
The official release says the new facility will open in 2030. The map pin remains listed as permitted.
Source: UC San Francisco, Jul 18, 2024
Worth knowing
- The map figure is the official $1.62 billion full-site modernization total in the July 18, 2024 UCSF release. The same official release states that the hospital building alone is $1.49 billion. That official building-only figure is recorded here and is not used to replace the map total.
- Expected construction-employment figures mentioned in the official release are not added to the map total.
- The official release is an approval announcement. This pass did not find a later official construction-start confirmation in that release. The map pin remains listed as permitted, and this page does not change any map stage field.