UCSF Helen Diller Hospital, Parnassus Heights
A $4.3 billion, 15-story hospital under construction at Parnassus Heights, with first patients expected in 2030.
Show on the map: UCSF Helen Diller Hospital, Parnassus Heights
- Investment$4.3 billion, the figure used on the map, from UCSF's April 27, 2024 groundbreakingUniversity of California, San Francisco, Apr 27, 2024
- ScopeA 15-story, 880,000 square-foot hospital that will raise UCSF Health capacity 37% to 682 beds, add 22 operating rooms (40 overall), and add 31 emergency beds (70 overall)University of California, San Francisco, Apr 27, 2024
- GroundbreakingUCSF Health broke ground on April 27, 2024, and said the hospital would open in 2030University of California, San Francisco, Apr 27, 2024
- ProgressA November 12, 2026 UCSF Real Estate construction update said structural steel was then being installed on levels 6 and 7, with steel erection continuing into mid-2027, completion expected by 2029, and activation and the first patient in 2030UCSF Real Estate, Nov 12, 2026
Next gate
Complete the structure and prepare for 2030 opening
Steel erection into mid-2027; completion expected in 2029; first patient in 2030
The November 2026 official update said steel erection will continue into mid-2027, with completion expected by 2029, followed by activation and the first patient in 2030.
Every step so far, and what comes next
-
DoneApril 27, 2024
Groundbreaking at Parnassus Heights
UCSF Health broke ground on the $4.3 billion, 15-story Helen Diller Hospital and said it would open in 2030.
Source: University of California, San Francisco, Apr 27, 2024
-
DoneNovember 2026
Steel reaches levels 6 and 7
UCSF Real Estate said structural steel installation was underway on levels 6 and 7.
Source: UCSF Real Estate, Nov 12, 2026
-
Next2029
Hospital completion expected
The completion year given in the November 2026 official construction update, ahead of activation and first patient in 2030.
Source: UCSF Real Estate, Nov 12, 2026
-
Expected2030
First patient
The opening and first-patient year given in 2024 and repeated in the November 2026 update.
Source: University of California, San Francisco, Apr 27, 2024
Worth knowing
- The $4.3 billion figure and 2030 opening were announced at groundbreaking in 2024. The November 2026 update keeps first patient in 2030 and adds a 2029 completion target. Those dates may still move.
- The 2024 announcement also described a related research and academic building expected to open in 2028 on the western edge of campus. That building is part of the wider Parnassus plan, not separately priced on this page.