Unified Parkway data center campus, Sutton
A proposed 10 building data center campus drawing about 900 megawatts, not yet filed or approved.
Show on the map: Sutton data center campus
- Developer estimateMore than $16 billion of private investmentTown of Sutton, Massachusetts, Nov 9, 2026
- PowerAbout 900 megawatts at full build-outTown of Sutton, Massachusetts, Nov 9, 2026
- ScheduleFirst two buildings in 2029, then two more each year through 2033Town of Sutton, Massachusetts, Nov 9, 2026
Next gate
Zoning change and application
No date published
Data centers are not allowed under Sutton's current zoning, so a zoning change needs a two-thirds Town Meeting vote before an application can move.
Every step so far, and what comes next
-
DoneNov 9, 2026
Town Manager sends a preliminary review to the Select Board
The Sutton Town Manager's memo cites the developer's estimate of more than $16 billion and says no application has been filed and nothing is approved.
-
NextNo date published
Zoning change and application
Data centers are not allowed under Sutton's current zoning, so a zoning change needs a two-thirds Town Meeting vote before an application can move.
Worth knowing
- The figure is the developer's estimate as reported in the town memo: about $675 million of real property plus roughly $1 billion of computer equipment per building. The town's own tax valuation is far lower.
Last checked Nov 28, 2026. We add a step when it happens and link the source.