United Terminal B Transformation Program, George Bush Intercontinental Airport
A $2.6 billion Terminal B program whose new 22 gate North concourse opened in October 2026, while work on Terminal B South continues toward 48 United gates in all.
Show on the map: United Terminal B Transformation Program, George Bush Intercontinental Airport
- InvestmentUnited's October 21, 2026 release called the new Terminal B North concourse the centerpiece of the airline's broader $2.6 billion Terminal B Transformation Program, the figure used on the mapUnited Airlines, Oct 21, 2026
- Terminal B North openingThe October 21, 2026 official release said United previewed the new three-level, 765,000 square foot, 22 mainline-gate Terminal B North concourse, and that it would open to the public the next day, October 22, 2026. The concourse replaces facilities dating back to 1969United Airlines, Oct 21, 2026
- Remaining workTogether with improvements to the Terminal B South concourse, United said it will have 48 gates in Terminal B. The official release does not give a completion date for the South work. United also said it has invested more than $3.5 billion in Houston's airport since 2015, a broader total that includes other facilities and is not the map figureUnited Airlines, Oct 21, 2026
Next gate
Terminal B South improvements continue
No official South completion date in the October 21, 2026 release
Official materials confirm that Terminal B North is open and that South concourse improvements are part of the same $2.6 billion program, but they do not state when the South work will be finished.
Every step so far, and what comes next
-
NextNo official date published
Terminal B South improvements continue
The same official release said improvements to Terminal B South are part of the program that will give United 48 gates in Terminal B, without giving a South completion date.
Source: United Airlines, Oct 21, 2026
-
DoneOctober 22, 2026
Terminal B North opened to the public
United's October 21, 2026 release said the new 22 gate, 765,000 square foot North concourse would open to the public the next day.
Source: United Airlines, Oct 21, 2026
Worth knowing
- The map figure is the $2.6 billion Terminal B Transformation Program. United's more than $3.5 billion investment in Houston airports since 2015 is a broader total that includes other facilities and is not added to, or substituted for, the map figure.
- The tracker stage reflects the official opening of Terminal B North. The map pin remains listed as under construction because South concourse work continues, and this page does not change any map stage field.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.