Track your favorite projects · AI data centers

Vantage Lighthouse campus

Vantage Data Centers, for Oracle and OpenAI · Port Washington, Ozaukee County, Wisconsin

Under construction, about a quarter done

Four Stargate data centers, close to 1 GW, rising on Port Washington's north side by Lake Michigan.

Show on the map: Vantage Lighthouse campus, Port Washington

Next gate

First turnover to Oracle and OpenAI

End of 2027

Vantage expects to start handing over buildings in phases at the end of 2027.

Every step so far, and what comes next

  1. DoneOct 22, 2025

    Announced

    Vantage, Oracle and OpenAI named Port Washington as a Stargate site.

  2. DoneJan 19, 2026

    First foundation pour

    Concrete started on the first building.

  3. DoneMay 12, 2026

    First building steel topped out

    The last steel went into the first of four buildings.

  4. DoneSep 2026

    20% to 25% complete

    Vantage's construction vice president gave the figure on a public tour.

  5. NextEnd of 2027

    Phased turnover begins

    Buildings go live in parts as construction finishes.

  6. Expected2028

    Campus complete

    Vantage's original schedule.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.