Vantage Lighthouse campus
Four Stargate data centers, close to 1 GW, rising on Port Washington's north side by Lake Michigan.
Show on the map: Vantage Lighthouse campus, Port Washington
- Investment$15 billion+Vantage Data Centers, Oct 22, 2025
- CapacityFour data centers with close to 1 GW of AI capacityVantage Data Centers, Oct 22, 2025
- Progress20% to 25% complete in September 2026, with 2,800 to 3,000 workers on site a dayOzaukee Press, Sep 23, 2026
- Local upgradesAt least $175 million for water, sewer and power infrastructureVantage Data Centers, Oct 22, 2025
Next gate
First turnover to Oracle and OpenAI
End of 2027
Vantage expects to start handing over buildings in phases at the end of 2027.
Every step so far, and what comes next
-
DoneOct 22, 2025
Announced
Vantage, Oracle and OpenAI named Port Washington as a Stargate site.
-
DoneJan 19, 2026
First foundation pour
Concrete started on the first building.
Source: Ozaukee Press, Sep 23, 2026
-
DoneMay 12, 2026
First building steel topped out
The last steel went into the first of four buildings.
Source: Ozaukee Press, Sep 23, 2026
-
DoneSep 2026
20% to 25% complete
Vantage's construction vice president gave the figure on a public tour.
Source: Ozaukee Press, Sep 23, 2026
-
NextEnd of 2027
Phased turnover begins
Buildings go live in parts as construction finishes.
Source: Ozaukee Press, Sep 23, 2026
-
Expected2028
Campus complete
Vantage's original schedule.
Worth knowing
- Vantage says $15 billion+; the map counts $15 billion.
- Power delivery depends on new transmission and generation that is still in approvals.
Last checked Nov 23, 2026. We add a step when it happens and link the source.