Vantage Quincy campus
An official October 18, 2023 Vantage Data Centers release announced delivery of the third and final facility on its 89-megawatt Quincy campus, and the official title describes a $1 billion campus.
Show on the map: Vantage Quincy campus
- Official completion, capacity, and investmentThe official October 18, 2023 Vantage Data Centers news release, datelined Denver, announced the delivery of the third and final facility, WA13, on its Quincy, Washington, campus, called WA1. The official release title describes an 89-megawatt, $1 billion Quincy campus, and the official $1 billion figure is the amount used on the map. The official release says the 530,000-square-foot WA13 data center adds 64 megawatts of IT capacity to the 68-acre campus, now totaling 89 megawatts across nearly 775,000 square feet and three facilities. A quote in the same official release says that since entering the Quincy market in 2011, Vantage has invested more than $1 billion in the development of this campus.Vantage Data Centers, Oct 18, 2023
- Official construction of the final buildingThe official release says that since the start of construction in late 2022, the WA13 team completed more than 828,000 working hours, and that the company hosted a ribbon-cutting ceremony to celebrate delivery of the third and final facility.Vantage Data Centers, Oct 18, 2023
Next gate
Official October 18, 2023 release said the third and final Quincy facility had been delivered
After the official October 18, 2023 completion announcement
The official Vantage release announced delivery of the third and final facility on the 89-megawatt Quincy campus, described in the official title as a $1 billion campus. The map pin remains listed as operating.
Every step so far, and what comes next
-
DoneLate 2022
Construction begins on the final Quincy facility, WA13
The official October 18, 2023 release says construction of WA13 started in late 2022.
-
DoneOctober 18, 2023
Vantage announces delivery of the third and final Quincy facility
The official release announced delivery of WA13, bringing the 68-acre campus to 89 megawatts across three facilities, and described the campus in its title as a $1 billion development.
-
NextAfter the official October 18, 2023 completion announcement
Official October 18, 2023 release said the third and final Quincy facility had been delivered
The official Vantage release announced delivery of the third and final facility on the 89-megawatt Quincy campus, described in the official title as a $1 billion campus. The map pin remains listed as operating.
Worth knowing
- The map figure is $1 billion, matching the official October 18, 2023 release title. A quote in the same official release says Vantage has invested more than $1 billion in the campus. That official more-than wording is not used to replace the $1 billion map figure, and this page does not change any map usd, stage, or pledge field.
- An official Grant County assessed-value figure for the greater Quincy area, cited in the same release, is not a project cost and is not added.