Vineyard Wind 1 offshore wind farm
An 806 megawatt, 62-turbine farm, the first commercial-scale offshore wind project in U.S. waters, now generating power for Massachusetts.
Show on the map: Vineyard Wind 1 offshore wind farm
- InvestmentIn a January 15, 2026 federal court complaint, Vineyard Wind 1 LLC said it had spent more than $4.5 billion in engineering, planning, permitting, and construction costs. The map counts $4.5 billion as a floor, not a published final totalVineyard Wind 1 LLC, filed in the U.S. District Court for the District of Massachusetts, Jan 15, 2026
- CapacityThe official project page says Vineyard Wind 1 has 62 General Electric Haliade-X turbines, each capable of generating 13 megawatts, for 806 megawatts, and that the project generates power for more than 400,000 homes and businessesVineyard Wind, Nov 23, 2026
- LocationAbout 15 miles south of Martha's Vineyard and Nantucket, and 35 miles from mainland Massachusetts, in federal lease area OCS-A-0501. Two submarine cables land at Covell's Beach in BarnstableVineyard Wind, Nov 23, 2026
- StatusA September 16, 2026 Vineyard Wind release said all turbines were capable of producing power. The company's project page, checked on November 23, 2026, says the project has been built and is generating powerVineyard Wind, Sep 16, 2026
Next gate
Commercial operation continues
In service; official project page describes a completed, generating project
Vineyard Wind's September 16, 2026 release said all turbines were capable of producing power, and the official project page describes a built project that is generating electricity.
Every step so far, and what comes next
-
Done2021
Construction began
The January 15, 2026 complaint said project construction began in 2021 under a Construction and Operations Plan and related federal permits.
-
DoneSeptember 16, 2026
All turbines capable of producing power
Vineyard Wind said all turbines were capable of producing power and were providing energy to more than 400,000 homes and businesses.
Source: Vineyard Wind, Sep 16, 2026
-
NextIn service
Commercial operation continues
The official project page describes a completed project that is generating power.
Source: Vineyard Wind, Nov 23, 2026
Worth knowing
- The $4.5 billion figure is the amount the project company said it had spent as of its January 15, 2026 court filing, counted on the map as a floor. Official project pages reviewed for this pass did not publish a final total cost.
- The January 2026 complaint used a planned 800 megawatt figure. This page uses the official project page's 806 megawatts (62 turbines at 13 megawatts each).
- The map pin is onshore near the Barnstable landfall. The turbines are about 15 miles offshore.
Last checked Nov 23, 2026. We add a step when it happens and link the source.