Walnut Creek Wastewater Treatment Plant expansion, Austin
The City of Austin's official April 14, 2026 release marked the groundbreaking of a $1.5 billion expansion of the Walnut Creek Wastewater Treatment Plant, raising capacity from 75 million gallons a day to 100 million gallons a day.
Show on the map: Walnut Creek Wastewater Treatment Plant expansion, Austin
- Project cost and groundbreakingThe official April 14, 2026 City of Austin news release says Austin Water and city leaders broke ground that day on the $1.5 billion expansion of the Walnut Creek Wastewater Treatment Plant, the figure used on the map. The release says all improvements will be made while the plant remains fully operational, without interruptions.City of Austin, Apr 14, 2026
- Capacity and scopeThe official release says the plant today serves more than 50 percent of Austin and operates at a treatment capacity of 75 million gallons per day, and that the expansion will increase that capacity to 100 million gallons per day. Other official improvements include advanced treatment to reduce nutrients that contribute to algae growth, replacing chlorine gas with an ultraviolet disinfection system, advanced odor control, construction of a flood wall, and modernization of aging parts of the existing plant. The plant is located on FM 969.City of Austin, Apr 14, 2026
- Financing not a separate costThe official release says the expansion will be funded through a combination of federal and state low-interest loans, including up to $1 billion from the U.S. Environmental Protection Agency's Water Infrastructure Finance and Innovation Act (WIFIA) program and $59 million from the Texas Water Development Board Clean Water State Revolving Fund program, along with Austin Water's funding. Those official loan and fund amounts are financing sources and are not used to replace the official $1.5 billion project cost.City of Austin, Apr 14, 2026
Next gate
Official April 14, 2026 release marked the start of construction, with the plant staying in operation
After the official April 14, 2026 groundbreaking
The official City of Austin release marked the groundbreaking of the $1.5 billion expansion and said all improvements will be made while the plant remains fully operational. The map pin remains listed as under construction.
Every step so far, and what comes next
-
DoneApril 14, 2026
City of Austin breaks ground on the $1.5 billion Walnut Creek expansion
The official City of Austin release marked the groundbreaking of the $1.5 billion Walnut Creek Wastewater Treatment Plant expansion, the figure used on the map, which will raise treatment capacity from 75 million gallons per day to 100 million gallons per day while the plant stays in operation.
Source: City of Austin, Apr 14, 2026
-
NextAfter the official April 14, 2026 groundbreaking
Official April 14, 2026 release marked the start of construction, with the plant staying in operation
The official City of Austin release marked the groundbreaking of the $1.5 billion expansion and said all improvements will be made while the plant remains fully operational. The map pin remains listed as under construction.
Source: City of Austin, Apr 14, 2026
Worth knowing
- The map figure is the official $1.5 billion project cost stated in the City of Austin's April 14, 2026 groundbreaking announcement.
- Official financing figures in the same release, including up to $1 billion from the EPA WIFIA program and $59 million from the Texas Water Development Board Clean Water State Revolving Fund, are funding sources and are not used to replace the official $1.5 billion project cost.
Go deeper
Last checked Nov 24, 2026. We add a step when it happens and link the source.