Sound Transit West Seattle Link Extension
A light rail extension now advancing in final design without Avalon Station, with a March 2026 cost range of $4.9 billion to $5.3 billion in 2025 dollars.
Show on the map: Sound Transit West Seattle Link Extension
- InvestmentSound Transit's March 12, 2026 cost-savings update gave a March 2026 project cost range of $4.9 billion to $5.3 billion in 2025 dollars. The map uses the low end, $4.9 billionSound Transit, Mar 12, 2026
- ScopeThe original Sound Transit 3 plan described 4.1 miles of light rail with four stations. On May 28, 2026, the Sound Transit Board adopted an updated ST3 system plan that advances West Seattle Link with cost-saving design refinements, including the removal of Avalon StationSound Transit, May 28, 2026
- ScheduleA September 2026 project fact sheet shows design from 2025 to 2027, construction from 2027 to 2035, and service starting in 2035Sound Transit, Sep 2026
- RidersThe September 2026 fact sheet says the extension will serve more than 20,000 riders a day and will cut travel time in half from West Seattle to Westlake Station once connected to the regional Link systemSound Transit, Sep 2026
Next gate
Confirm design refinements with the Federal Transit Administration and continue final design
Final design runs through 2027, with construction shown as 2027 to 2035
The September 2026 fact sheet says the next step is confirming the design refinements, including the removal of Avalon Station, with the Federal Transit Administration, then continuing final design, permits, property acquisition, and early works ahead of major construction.
Every step so far, and what comes next
-
DoneMarch 12, 2026
Cost range lowered to $4.9 billion to $5.3 billion
A Sound Transit System Expansion Committee presentation showed the March 2026 estimate at $4.9 billion to $5.3 billion in 2025 dollars, down from earlier ranges, including options that would drop Avalon Station.
Source: Sound Transit, Mar 12, 2026
-
DoneMay 28, 2026
Board advances the project without Avalon Station
The Sound Transit Board adopted an updated ST3 system plan that lists West Seattle Link Extension, with no Avalon Station, among fully funded projects to be completed through construction.
Source: Sound Transit, May 28, 2026
-
DoneSeptember 2026
Fact sheet sets construction for 2027 to 2035
Sound Transit published a fact sheet showing design through 2027, construction from 2027 to 2035, and service in 2035, with FTA confirmation of the design refinements still ahead.
Source: Sound Transit, Sep 2026
-
Next2027
Confirm refinements with FTA and continue final design
The next steps described in the September 2026 fact sheet, ahead of the 2027 to 2035 construction window.
Source: Sound Transit, Sep 2026
Worth knowing
- The map counts $4.9 billion, the low end of the official March 2026 range of $4.9 billion to $5.3 billion in 2025 dollars. That range already reflected cost-savings work. A later single-point official budget was not found in the September 2026 fact sheet.
- The Board's May 28, 2026 action advances the project without Avalon Station. The September 2026 fact sheet says those refinements still need to be confirmed with the Federal Transit Administration.
- Construction from 2027 to 2035 and service in 2035 are the dates on the September 2026 fact sheet and may move.
- This page does not treat the project as under construction. Official materials describe final design now, with major construction not shown until 2027.