Williams Socrates power project, New Albany
Two natural-gas power-generation sites in New Albany, commercialized as a $1.6 billion Williams Power Innovation project in 2025, with official later results describing work to bring Socrates fully online ahead of schedule.
Show on the map: Williams Socrates power project, New Albany
- InvestmentWilliams's official first-quarter 2025 results, dated May 5, 2025, say the company commercialized Socrates, a $1.6 billion Power Innovation project to serve growing AI demand in Ohio, backed by a long-term, fixed-price power purchase agreement. That official $1.6 billion figure is the one used on the map.Williams, May 5, 2025
- ScopeWilliams's official Socrates Power Solution Facilities page, reviewed on November 24, 2026, describes Socrates North and South as two power-generation sites in New Albany, Ohio, with a combined generating capacity of 400 megawatts, 200 megawatts at each site, and identifies the work as natural-gas generation. An official company fact sheet for the same project also describes it as a behind-the-meter power source. The living official page, as reviewed this pass, still describes the facilities as proposed and gives target in-service dates in the third and fourth quarters of 2026.Williams, Nov 24, 2026
- Later official statusA later official November 2, 2026 Williams release on third-quarter 2026 results says the Socrates' Plato North Power project was on track for in-service by mid-November and quotes the chief executive officer as saying the team was bringing Socrates fully online ahead of schedule. This pass did not find a later official confirmation, after that mid-November target, that the remaining work had entered service. The map pin remains listed as under construction.Williams, Nov 2, 2026
Next gate
Official mid-November 2026 in-service target for remaining Socrates work, not later confirmed in this pass
Mid-November 2026, according to the official November 2, 2026 Williams release
The official third-quarter 2026 results said the Socrates' Plato North Power project was on track for in-service by mid-November and that the company was bringing Socrates fully online ahead of schedule. This pass did not find a later official confirmation that the remaining work had entered service. The map pin remains listed as under construction.
Every step so far, and what comes next
-
DoneMay 5, 2025
Company commercializes Socrates as a $1.6 billion project
The official first-quarter 2025 results said Williams had commercialized Socrates, a $1.6 billion Power Innovation project in Ohio, the figure used on the map, backed by a long-term, fixed-price power purchase agreement.
Source: Williams, May 5, 2025
-
DoneNovember 2, 2026
Official results say Socrates is being brought fully online ahead of schedule
The official third-quarter 2026 results said the Socrates' Plato North Power project was on track for in-service by mid-November and that the company was bringing Socrates fully online ahead of schedule.
Source: Williams, Nov 2, 2026
-
NextMid-November 2026, according to the official November 2, 2026 release
Official in-service target for remaining Socrates work
The official release pointed to a mid-November in-service target. This pass did not find a later official confirmation that the remaining work had entered service. The map pin remains listed as under construction.
Source: Williams, Nov 2, 2026
Worth knowing
- The map figure is the official $1.6 billion commercialization figure in the May 5, 2025 Williams results. Later official materials reviewed this pass did not restate a different official project total, and none was invented.
- The official living project page, reviewed on November 24, 2026, still describes Socrates North and South as proposed facilities with target in-service dates in the third and fourth quarters of 2026. That living-page wording has not been used to override the later official November 2, 2026 earnings statements, and it has not been used to change the map stage.
- This pass did not find a later official confirmation, after the mid-November 2026 target in the November 2 release, that the remaining work had entered service. The map pin remains listed as under construction, and this page does not change any map stage field.
Last checked Nov 24, 2026. We add a step when it happens and link the source.