Willow oil project, National Petroleum Reserve
A North Slope oil development with process-module fabrication more than 75% complete and first oil targeted for early 2029.
Show on the map: Willow oil project, National Petroleum Reserve
- Investment$8.5 billion to $9.0 billion in total project capital guidance. The map counts the low end of that rangeConocoPhillips (SEC filing), Nov 6, 2025
- Module fabricationMore than 75% complete as of the company's Nov 5, 2026 quarterly updateConocoPhillips, Nov 5, 2026
- First oilOn track for early 2029, per the same updateConocoPhillips, Nov 5, 2026
Next gate
First oil
Early 2029 (company target)
ConocoPhillips said on Nov 5, 2026, that Willow remained on track for first oil in early 2029, with module fabrication more than 75% complete.
Every step so far, and what comes next
-
DoneNov 6, 2025
Capital guidance published
ConocoPhillips' third-quarter 2025 results materials gave total project capital guidance of $8.5 billion to $9.0 billion.
-
DoneNov 5, 2026
Module fabrication over 75% complete
The company said it had advanced Willow critical path items, with module fabrication more than 75% complete, and remained on track for first oil in early 2029.
Source: ConocoPhillips, Nov 5, 2026
-
NextEarly 2029
First oil
The company's published target as of November 2026.
Source: ConocoPhillips, Nov 5, 2026
Worth knowing
- The capital range is from ConocoPhillips' Nov 6, 2025 guidance. The Nov 5, 2026 quarterly release updated progress but did not publish a new total capital figure.
- The map counts $8.5 billion, the low end of the range.
- Dates are company targets.
Last checked Nov 23, 2026. We add a step when it happens and link the source.