Grid United Wyoming Intertie transmission line

Grid United · A proposed route from the Aeolus substation near Medicine Bow to the Laramie River Station area near Wheatland, across Carbon, Albany, and Platte counties, Wyoming (the map pin is at Laramie River Station)

Announced, still in planning

A planned 106-mile, 1,800 megawatt HVDC line that would connect the eastern and western grids in Wyoming, still in planning, with a conditional federal loan of up to $2.8 billion.

Show on the map: Grid United Wyoming Intertie transmission line

Next gate

Permits, right-of-way, and capacity contracts needed before construction

Earliest construction start around 2030, per the official fact-sheet timeline

The official overview says construction starts only after land rights and regulatory approvals. The October 20, 2026 fact sheet places the earliest start of transmission-line and converter-station construction around 2030, with commercial operation later and contingent on HVDC procurement.

Every step so far, and what comes next

  1. DoneOctober 2026

    Official overview describes a $3 billion, 106-mile plan

    Grid United published an overview of the proposed 106-mile, 1,800 megawatt HVDC line, still in planning and development.

  2. DoneNovember 17, 2026

    Conditional DOE loan of up to $2.8 billion

    The Department of Energy announced a conditional loan commitment. Funding would start only after notice to proceed and the start of construction.

  3. NextAround 2030

    Earliest construction start, if approvals are in hand

    The earliest start shown on the official fact-sheet timeline for the line and converter station.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.