Grid United Wyoming Intertie transmission line
A planned 106-mile, 1,800 megawatt HVDC line that would connect the eastern and western grids in Wyoming, still in planning, with a conditional federal loan of up to $2.8 billion.
Show on the map: Grid United Wyoming Intertie transmission line
- Official project costGrid United's October 22, 2026 project overview describes Wyoming Intertie as an approximately $3 billion investment in Wyoming. The map counts $4 billion, a higher figure that was not used as an official total in the company overview or in the Department of Energy loan announcement reviewed for this passGrid United / Wyoming Intertie, Oct 22, 2026
- ScopeThe same overview describes an approximately 106-mile, 1,800 megawatt high-voltage direct-current line connecting the Eastern and Western Interconnections within Wyoming, from the Aeolus area to Laramie River, with a back-to-back converter stationGrid United / Wyoming Intertie, Oct 22, 2026
- Federal loanOn November 17, 2026, the Department of Energy announced a conditional loan commitment of up to $2.8 billion. An official project fact sheet says the loan would cover 80% of construction costs, is for 30 years, and would begin funding only after notice to proceed and the start of construction. Closing still requires full right-of-way, commercial capacity contracts, and federal, state, and local permitsU.S. Department of Energy, Nov 17, 2026
- StatusThe October 22, 2026 overview says the project is in the planning and development phase, that the route will remain proposed until it receives county, state, and federal approvals, and that construction will commence after land rights and regulatory approvals are secured. The companion fact-sheet timeline shows the earliest start of line and converter-station construction around 2030Grid United / Wyoming Intertie, Oct 22, 2026
Next gate
Permits, right-of-way, and capacity contracts needed before construction
Earliest construction start around 2030, per the official fact-sheet timeline
The official overview says construction starts only after land rights and regulatory approvals. The October 20, 2026 fact sheet places the earliest start of transmission-line and converter-station construction around 2030, with commercial operation later and contingent on HVDC procurement.
Every step so far, and what comes next
-
DoneOctober 2026
Official overview describes a $3 billion, 106-mile plan
Grid United published an overview of the proposed 106-mile, 1,800 megawatt HVDC line, still in planning and development.
-
DoneNovember 17, 2026
Conditional DOE loan of up to $2.8 billion
The Department of Energy announced a conditional loan commitment. Funding would start only after notice to proceed and the start of construction.
-
NextAround 2030
Earliest construction start, if approvals are in hand
The earliest start shown on the official fact-sheet timeline for the line and converter station.
Worth knowing
- The map counts $4 billion. Official Grid United materials reviewed here describe an approximately $3 billion investment. The Department of Energy figure is a conditional loan of up to $2.8 billion, covering 80% of construction costs, not a published $4 billion project total.
- The loan is conditional. It is not a closed financing or a construction notice to proceed.
- The route is still proposed. This page does not treat construction as started.
- The map pin is at Laramie River Station in Platte County. The line would run west toward Aeolus in Carbon County.
Last checked Nov 23, 2026. We add a step when it happens and link the source.