Uranium Processing Facility, Y-12

National Nuclear Security Administration · Y-12 National Security Complex, Oak Ridge, Tennessee

Under construction, early equipment testing

A new uranium processing plant at Oak Ridge, under construction to replace a 1945 building, with first furnaces now in testing.

Show on the map: Uranium Processing Facility, Y-12

Next gate

Remaining furnaces started up

Coming months after Oct 2026

After the first sintering and microwave furnaces were powered in October 2026, Y-12 said the remaining furnace technologies would be started up in the coming months.

Every step so far, and what comes next

  1. DoneDecember 2024

    Project rebaselined

    NNSA received approval to rebaseline the project at $10.35 billion, with full operations expected in 2034.

  2. DoneOct 8, 2026

    First furnaces powered

    Y-12 started the first sintering and microwave furnaces, the start of the furnace testing program.

  3. NextComing months after Oct 2026

    Remaining furnaces started up

    Y-12's stated next step in furnace testing, including work at full operating temperatures and tests with surrogate materials.

  4. Expected2034

    Fully operational

    NNSA's expected date for full operations, as reported by GAO.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.