Puget Sound Naval Shipyard Multi-Mission Dry Dock
A new dry dock in Bremerton built for Ford-class aircraft carriers and Virginia-class submarines, the only one in the Pacific able to take a Ford-class carrier, with $14.76 billion requested and completion planned for 2038.
Show on the map: Puget Sound Naval Shipyard Multi-Mission Dry Dock
- Investment$14.76 billion, the total project authorization the Navy requested in its fiscal 2027 budget for the dry dock, new piers and relocated shipyard facilitiesU.S. Government Accountability Office, Sep 25, 2026
- What gets builtA pressure relieved dry dock chamber of about 1,210 by 210 by 62 feet with portal crane access, replacing a 1962 dry dock built for Forrestal-class carriers; it will be the only dry dock in the Pacific able to take a Ford-class carrierU.S. Navy, PEO Industrial Infrastructure (SIOP), Apr 15, 2025
- Ships it servesFord-class and Nimitz-class aircraft carriers and other surface and subsurface ships; the GAO says the plans include capacity for Virginia-class and Ford-class maintenanceU.S. Government Accountability Office, Sep 25, 2026
- Construction contractNAVFAC Northwest solicitation issued September 30, 2026 for multiple award construction contracts with a $15 billion ceiling over up to 10 years, major task orders of $2 billion to $6 billion, proposals due December 1, 2026NAVFAC Northwest on SAM.gov, Sep 30, 2026
- ScheduleSite preparation demolition planned for 2027, dry dock construction for 2030 and completion for 2038U.S. Government Accountability Office, Sep 25, 2026
Next gate
Contract proposals due
December 1, 2026 (NAVFAC)
Proposals for NAVFAC Northwest's Multi-Mission Dry Dock multiple award construction contract (solicitation N4425526R0005) are due December 1, 2026 at noon Pacific time. Site preparation demolition follows in 2027 under Navy plans reviewed by the GAO.
Every step so far, and what comes next
-
DoneSeptember 30, 2026
Construction contract solicitation issued
NAVFAC Northwest issued the Multi-Mission Dry Dock multiple award construction contract solicitation with a $15 billion ceiling.
-
NextDecember 1, 2026
Contract proposals due
Proposals for the multiple award construction contract are due December 1, 2026 at noon Pacific time.
-
Expected2027 (Navy plan)
Site preparation demolition
Navy plans reviewed by the GAO set site preparation demolition to begin in 2027.
-
Expected2038 (Navy plan)
Dry dock completed
The Navy plans to complete the project in 2038, after dry dock construction starts in 2030.
Worth knowing
- The map figure is the $14.76 billion total project authorization in the Navy's fiscal 2027 budget request, as reported by the GAO. The $15 billion is the ceiling of the construction contract vehicle and is not added.
- Stage is announced: proposals are due December 1, 2026 and the environmental Record of Decision is still pending, so construction has not started.
- Part of the Navy's Shipyard Infrastructure Optimization Program, which the GAO says will surpass $200 billion across all four public shipyards.